Jed and Nate put in two good days out at the site this President's Day weekend, and with Ma Slack in town Pa Slack found himself with a crew of four. We were able to complete the tilework (see other post), make some substantial progress on the mudding/taping of the second floor, install blocking around all of the windows (which will facilitate trimming them out in the coming weeks), and sheetrock/trim around the skylights. Nate has agreed to stick around for the remainder of the week, and with Deb and Dave due to arrive Friday we are putting together quite a string of uber-productive days!!